Facility B21-615, a newly constructed building located at the Central Facilities Area (CFA) Gun Range, currently has limited access. At present, en…
The Antares R1 Mark-0 Reactor Project at Idaho National Laboratory (INL) involves deploying and operating the Antares R1 Mark-0, a small, high-temp…
Project Introduction Standard Nuclear proposes to conduct site characterization activities in support of the planned Standard Nuclear–Idaho (SN-I) …
Proposed activities include: Siting, construction, modification, operation, and decommissioning of facilities for small-scale research and developm…
The Idaho National Laboratory (INL) will design, fabricate, and test silicon carbide (SiC) fuel cladding capsules to support transient testing unde…
This document outlines the job requirements for the Environmental Review Process (ERP) concerning (4) Launch Pad temporary sign sites, the skids on…
The purpose of this Project Task Statement is to define the scope of work required to support Deployable Energy’s experimental objectives. This inc…
The project will expand the existing network of fire-weather stations and wildfire detection cameras, and install AI-enabled grid monitors on feede…
Bonneville Power Administration (BPA) proposes to fund the Nez Perce Tribe (NPT) to replace an undersized bridge across Elk Creek and a concrete si…
The Idaho National Laboratory (INL) will collaborate with Lawrence Livermore National Laboratory (LLNL) to support the design and execution of an e…