Rogue-Gold Beach No. 2 Disconnect Switch Replacement
CX(s) Applied: B4.6
Date: 01/08/2013
Location(s): Oregon
Offices(s): Bonneville Power Administration
Existing Regulations
B4.6: Additions and modifications to transmission facilities
Additions or modifications to electric power transmission facilities within a previously disturbed or developed facility area. Covered activities include, but are not limited to, switchyard rock grounding upgrades, secondary containment projects, paving projects, seismic upgrading, tower modifications, load shaping projects (such as the installation and use of flywheels and battery arrays), changing insulators, and replacement of poles, circuit breakers, conductors, transformers, and crossarms.
Previous Regulations
Categorical Exclusion Determinations dated before November 14th, 2011 were issued under previous DOE NEPA regulations. See the Notice of Final Rulemaking (76 FR 63763, 10/13/2011) for information changes to this categorical exclusion.
DOCUMENTS AVAILABLE FOR DOWNLOAD
-
January 8, 2013
-
December 13, 2012
Ault Substation Drainage Swale Construction
CX(s) Applied: B4.6
Date: 12/13/2012
Location(s): Colorado
Offices(s): Western Area Power Administration-Rocky Mountain Region -
December 11, 2012
Holyoke Substation Transformer Replacement
CX(s) Applied: B4.6
Date: 12/11/2012
Location(s): Colorado
Offices(s): Western Area Power Administration-Rocky Mountain Region -
December 6, 2012
Lane Substation 500/230-kV Transformer Phase Separation Project
CX(s) Applied: B4.6
Date: 12/06/2012
Location(s): Oregon
Offices(s): Bonneville Power Administration -
December 3, 2012
FY13 Environmental Drainage Upgrades at Bonneville Power Administration’s Clatsop, Garrison, Lexington, Mapleton, Ovando, Pearl, and Wren Substations
CX(s) Applied: B4.6
Date: 12/03/2012
Location(s): Oregon, Montana, Washington, Oregon, Oregon
Offices(s): Bonneville Power Administration -
November 29, 2012
Spring Creek – Wine County No. 1 Transmission Tower Relocation
CX(s) Applied: B4.6
Date: 11/29/2012
Location(s): Oregon
Offices(s): Bonneville Power Administration -
November 1, 2012
Tucannon River Substation Expansion Project
CX(s) Applied: B4.6
Date: 11/01/2012
Location(s): Washington
Offices(s): Bonneville Power Administration -
October 29, 2012
Relay and Switchboard Panel Replacements
CX(s) Applied: B4.6
Date: 10/29/2012
Location(s): Arkansas
Offices(s): Southwestern Power Administration -
September 24, 2012
Ross Transformer Oil Terminal Upgrade
CX(s) Applied: B4.6
Date: 09/24/2012
Location(s): Washington
Offices(s): Bonneville Power Administration -
September 20, 2012
Willow Creek - Granby Tap 2.4 Kilovolt Distribution Line Structure 0/3A Pole Replacement Project
CX(s) Applied: B4.6
Date: 09/20/2012
Location(s): Colorado
Offices(s): Western Area Power Administration-Rocky Mountain Region -
September 14, 2012
Port Angeles Substation Equipment Additions
CX(s) Applied: B4.6
Date: 09/14/2012
Location(s): Washington
Offices(s): Bonneville Power Administration -
August 24, 2012
Building 28-33 External Electrical Upgrades
CX(s) Applied: B1.23, B2.5, B4.6, B4.13
Date: 08/24/2012
Location(s): Oregon
Offices(s): National Energy Technology Laboratory -
August 20, 2012
Building 22 Electrical Upgrades
CX(s) Applied: B2.5, B4.6
Date: 08/20/2012
Location(s): Oregon
Offices(s): National Energy Technology Laboratory -
August 20, 2012
Building 29-31 Internal Electrical Upgrades
CX(s) Applied: B2.1, B2.5, B4.6
Date: 08/20/2012
Location(s): Oregon
Offices(s): National Energy Technology Laboratory -
August 9, 2012
Optimization of Electrical Power at the Portsmouth Gaseous Diffusion Facility
CX(s) Applied: B4.6, B4.11
Date: 08/09/2012
Location(s): Ohio
Offices(s): Portsmouth Paducah Project Office -
July 30, 2012
Pilot Butte-La Pine No. 1 Wood Pole Replacement Project
CX(s) Applied: B4.6
Date: 07/30/2012
Location(s): Oregon
Offices(s): Bonneville Power Administration -
July 30, 2012
Line Switch Replacements at Guernsey Rural, Worland, Refinery, Box Butte, and Morrill Taps
CX(s) Applied: B4.6, B4.11
Date: 07/30/2012
Location(s): Wyoming, Nebraska
Offices(s): Western Area Power Administration-Rocky Mountain Region -
July 25, 2012
Line Switch Replacements at Chappell and Julesburg Taps in Deuel County, Nebraska and Kersey Tap in Weld, Colorado
CX(s) Applied: B4.6, B4.11
Date: 07/25/2012
Location(s): Nebraska, Colorado
Offices(s): Western Area Power Administration-Rocky Mountain Region -
July 25, 2012
Midway Substation 230 Kilovolt Upgrades El Paso County, Colorado
CX(s) Applied: B4.6, B4.11
Date: 07/25/2012
Location(s): Colorado
Offices(s): Western Area Power Administration-Rocky Mountain Region -
July 19, 2012
Hot Springs Substation Gravity Drain Install
CX(s) Applied: B4.6
Date: 07/19/2012
Location(s): Montana
Offices(s): Bonneville Power Administration -
July 2, 2012
Boysen-Thermopolis 115 Kilowolt Transmission Line Structure 15/6 Pole Replacement Project Fremont County, Wyoming
CX(s) Applied: B4.6
Date: 07/02/2012
Location(s): Wyoming
Offices(s): Western Area Power Administration-Rocky Mountain Region -
June 28, 2012
Lancaster Line and Load Project
CX(s) Applied: B4.6, B4.7
Date: 06/28/2012
Location(s): Idaho
Offices(s): Bonneville Power Administration -
June 20, 2012
Airport to Boyd 115 Kilovolt Transmission Line Structure Replacements Larimer County, Colorado
CX(s) Applied: B1.3, B4.6
Date: 06/20/2012
Location(s): Colorado
Offices(s): Western Area Power Administration-Rocky Mountain Region -
June 18, 2012
Platform Construction for Power Pole Work
CX(s) Applied: B1.13, B2.5, B4.6
Date: 06/18/2012
Location(s): Wyoming
Offices(s): RMOTC -
June 18, 2012
Platform Construction for Power Pole Work
CX(s) Applied: B1.13, B2.5, B4.6
Date: 06/18/2012
Location(s): Wyoming
Offices(s): RMOTC