You are here

Enforcement Letter, BWXT Y-12 - June 15, 2006

June 15, 2006
Enforcement Letter issued to BWXT Y-12 related to Quality Assurance Deficiencies in construction activities at the Y-12 National Security Complex Highly Enriched Uranium Manufacturing Facility

The Department of Energy’s Office of Price-Anderson Enforcement (OE) has conducted a preliminary evaluation of the deficiencies described in Noncompliance Tracking System (NTS) report NTS-Y12--BWXT-Y12NUCLEAR-2006-0003. Our evaluation included review of the causal analysis, associated corrective action plan, and discussion with you and other site personnel.