The Hanford site, a 580-square-mile section of semi-arid desert in southeast Washington, was established in 1943 as part of the Manhattan Project to produce plutonium for national defense. Hanford produced nearly two-thirds of the plutonium used in the US nuclear weapons stockpile, including materials for the Trinity Test and atomic bombs used to help end World War II. Watch the video below to learn more about the Hanford site.
Hanford News
-
Hanford Site workers recently demolished a 6,000-square-foot water treatment facility near the Columbia River that once supported major risk-reduction work. July 15, 2025July 15, 2025
-
Approximately 2,000 gallons of treated tank waste from the Hanford Site have been safely and successfully solidified in grout and permanently disposed of at licensed commercial facilities. July 8, 2025July 8, 2025
-
Crews have finished installing a new high-voltage transmission line that improves the reliability of electrical service used to power waste treatment operations and other cleanup efforts at the Hanford Site. July 8, 2025July 8, 2025
-
A large office complex that served as a hub for Hanford cleanup efforts for more than 20 years has been torn down as part of the site's ongoing risk-reduction work. July 1, 2025July 1, 2025
-
Workers at the Hanford Site installed a new pump inside an underground waste-storage tank, advancing efforts to safely manage radioactive and chemical waste. June 24, 2025.June 24, 2025
-
More than 50 high school students stepped out of the classroom and into the world of science, technology, engineering and math during a recent hands-on event held at the Hanford Site’s Volpentest HAMMER Federal Training Center. June 24, 2025.June 24, 2025

Brian Harkins is the acting manager of the DOE Hanford Field Office. In this capacity, Harkins is responsible for an overall annual budget of $3 billion, and oversight of the contractors and more than 13,000 employees involved in cleanup of the 580-square-mile Hanford site. In his role as manager, Vance is responsible for the safe and environmentally acceptable cleanup of the site, including groundwater remediation; hazardous waste and facilities decontamination and disposal operations; treatment and disposal of radioactive chemical liquid waste; and the design, construction and commissioning of the world’s largest complex of nuclear vitrification facilities, the Waste Treatment and Immobilization Plant.
High-Level Budget Information
Office | FY22 Enacted (in the millions) | FY23 Request (in the millions) | FY23 Enacted (in the millions) | FY23 Request (in the millions) | FY24 Enacted (in the millions) | FY25 Requested (in the millions) |
Office of River Protection | $1,645 | $1,604 | $1,730 | $1,975 | $1,890 | $2,001 |
Richland Operations Office | $1,052 | $917 | $1,114 | $1,025 | $1,146 | $1,107 |
For more information on the Office of Environmental Management's budget process and performance check out the Budget & Performance page.
