Preliminary Notice of Violation, Battelle Energy Alliance, LLC - EA-2007-06

Preliminary Notice of Violation issued to Battelle Energy Alliance, LLC, related to Unplanned Shutdown and Restart of the Neutron Radiography Reactor at the Idaho National Laboratory

September 18, 2007
Preliminary Notice of Violation, BWXT Y-12 LLC - EA-2007-04

Preliminary Notice of Violation issued to BWXT Y-12, LLC, related to Criticality Safety Controls at the Y-12 National Security Complex

February 16, 2007
Preliminary Notice of Violation,University of California - EA-2006-05

Notice of Violation issued to the University of California related to Operational Performance at the Los Alamos National Laboratory

November 21, 2006
Preliminary Notice of Violation, BWXT Pantex, LLC - EA-2006-04

Issued to BWXT Pantex, LLC, related to Quality Assurance and Safety Basis Requirements Violations at the Pantex Plant

November 16, 2006
Preliminary Notice of Violation, CH2M Hill Hanford Group, Inc. - EA-2006-06

Preliminary Notice of Violation issued to CH2M Hill Hanford Group, Inc., related to Radiological Contamination Events at the Hanford Site Tank Farms

February 23, 2006
Preliminary Notice of Violation, University of California - EA-2006-01

Preliminary Notice of Violation issued to the University of California related to Radiological Uptakes, a Radioactive Material Spill, and Radiological Protection Program, Quality Assurance, and Safety Basis Deficiencies at the Lawrence Livermore National Laboratory

October 4, 2004
Enforcement Letter, CH2M Hill - October 4, 2004

Issued to CH2M Hill related to at a Lapse in Dosimetry Accreditation at the Separations Process Research Unit

August 12, 2004
Enforcement Letter, Kaiser-Hill Company - August 12, 2004

Enforcement Letter issued to Kaiser-Hill Company, LLC related to a Water Treatment System Breach and Foam Fire at the Rocky Flats Environmental Technology Site

March 25, 2004
Enforcement Letter, Bechtel National Inc - March 25, 2004

Enforcement Letter issued to Bechtel National, Inc., related to Concrete Work Issues at the Waste Treatment and Immobilization Plant at the Hanford Site

November 14, 2003
Enforcement Letter, Westinghouse Savannah River Company - November 14, 2003

Enforcement Letter issued to Westinghouse Savannah River Company related to Criticality Safety Violations at the Savannah River Site