50% of the incremental cost of the project(s) included in the application.
The maximum annual payment cap is determined per account, by the applicable MID electric rate schedule: $15,000 (GS-1); $25,000 (P-3); $50,000 (GS-2); $125,000 (GS-TOU); $250,000 (GS-3); $500,000 (IC-25).
12/15/2013
Whole Building Approach: $425/kW reduced or $0.08/kWh reduced
Systems Approach (Lighting): $250/kW reduced or $0.04/kWh reduced
Systems Approach (Other-Durable): $500/kW reduced or $0.10/kWh reduced
Systems Approach (Other-Variable): $350/kW reduced or $0.07/kWh reduced
The MPower Business New Construction Rebate Program is available to commercial, industrial, or agricultural customers that presently or will receive electric service from MID. Accounts billed on FL or SL rate schedules are not eligible for this program. To be eligible for this program, replacement projects must meet the following requirements: reduce electrical energy usage relative to the baseline, operate for a minimum of 5 years after installation, not be completed prior to submitting an application, and be completed within one year of submitting an application with a minimum rebate amount of $250. Customers should choose the rebate amount formula that gives them the greatest value for kW reduction during peak periods and kWh reduction during the first year. Rebates will be paid in one or two installments depending on the performance period. For further program details and instructions on how to apply, customers should download the application form located on the program web site.
Almost any project that involves installation of new high-efficiency equipment in new facilities or
during the major remodel or expansion of existing facilities may be eligible. Details are listed on the program application.
http://www.dsireusa.org/incentives/incentive.cfm?Incentive_Code=CA181F