Re: Potomac River Generating Station Department of Energy, Case No. EO-05-01: Potomac Electric Power Company (PEPCO) Concerning Planned Outages of the 230 kV circuits

Docket No. EO-05-01. Order No. 202-07-02: Pursuant to the Department of Energy's Order No. 202-05-3 issued December 20, 2005 ("DOE Potomac River Order"), Pepco has filed notice of the planned outages, in sequence during January 2006, of each of the two 230 kV circuits serving the downtown area of the District of Columbia. Earlier scheduled maintenance on these lines was postponed because of the shutdown of Mirant's Potomac River Generating Plant, but a recent forced outage on one of the lines makes it imprudent to delay maintenance any longer.