Recovery Act-Fault Current Limiting (FCL) Superconducting TransformerCX(s) Applied: A9, B3.6, B4.11Date: 07/16/2010Location(s): Irvine, CaliforniaOffice(s): Electricity Delivery and Energy Reliability, National Energy Technology Laboratory
Office of NEPA Policy and Compliance
July 16, 2010CX(s) Applied: A9, B3.6, B4.11
Date: 07/16/2010
Location(s): Irvine, California
Office(s): Electricity Delivery and Energy Reliability, National Energy Technology Laboratory
Southern California Edison will install and operate a prototype fault current limiting superconducting transformer rated 28 megavolt ampere, 66 kilovolt/12 kilovolt service, built by Waukesha Electric, in their MacArthur substation as a demonstration.