BP Cherry Point Cogeneration Project
Office of NEPA Policy and Compliance
September 5, 2003BP Cherry Point Cogeneration Project
BP West Coast Products, LLC proposes to construct and operate a 720-megawatt, natural-gas-fired, combined-cycle cogeneration facility on land adjacent to its BP Cherry Point Refinery. Approximately 195 acres of undeveloped land would be converted for the cogeneration facility; gas, water, wastewater, and steam pipelines; construction laydown areas; access roads; and wetland mitigation areas.This Draft EIS assesses the existing natural and built environment, evaluates the potential environmental impacts and economic benefits of the proposed action, and identifies mitigation measures to compensate for the unavoidable impacts. Alternative project sites, power-generating and pollution-control technologies, and the No Action Alternative also are described.