Interconnection of the Sutter Power Project With the Western Area Power Administration’s Keswick-Elverta/Olinda-Elverta 230-Kilovolt Double-Circuit Transmission Line (June 1999)

Record of Decision for the Interconnection of the Sutter Power Project With the Western Area Power Administration's Keswick-Elverta/Olinda-Elverta 230-Kilovolt Double-Circuit Transmission Line. The Western Area Power Administration (Western) prepared this Record of Decision in response to a request submitted to Western for a direct interconnection of Calpine Corporation’s (Calpine) proposed Sutter Power Project (SPP) with Western’s electric transmission system.