You are here

EA-1950: Finding of No Significant Impact and Mitigation Action Plan

Grand Coulee-Creston Transmission Line Rebuild; Grant and Lincoln Counties, Washington

Bonneville Power Administration issued a finding of no significant impact and a mitigation action plan for rebuilding approximately 28 miles of the Grand Coulee-Creston No. 1 115-kilovolt (kV) transmission line between Coulee Dam in Grant County and Creston in Lincoln County, Washington.