Albany-Burnt Woods and Santiam-Toledo Pole Replacement Project

This Mitigation Action Plan (MAP) is part of the Finding of No Significant Impact (FONSI) for the Albany-Burnt Woods and Santiam-Toledo Pole Replacement Project. The project involves replacing wood pole structures on about 26 miles of the Albany-Burnt Woods single-circuit, 115-kilovolt (kV) transmission line and about 21 miles of the Santiam-Toledo single circuit, 230-kVtransmission line in Linn, Benton and Lincoln counties, Oregon.