"Slatt Substation Meter and Communication Equipment Installation
CX(s) Applied: B1.7
Date: 05/05/2014
Location(s): Oregon
Offices(s): Bonneville Power Administration

Bonneville Power Administration (BPA) proposes to install revenue metering and some fiber optic cable at Slatt Substation. The proposed work would allow power from Portland General Electric’s (PGE) 500-megawatt Carty Gas Generation Station to be integrated into the Federal Columbia River transmission System via PGE’s existing Slatt-Boardman 500-kilovolt line.
"