GM Lithium Ion Battery Pack Manufacturing - Supplemental Work
CX(s) Applied: B4.13
Date: 05/21/2014
Location(s): Michigan
Offices(s): National Energy Technology Laboratory

GM Battery Assembly Plant - Design and installation of approximately 1,200 feet of electrical lines installed underground to carry power from the new approximately 100 square foot outdoor electrical substation.