Cheyenne-Snowy Range 230-Kilovolt Central Rig Upgrade Eaglenet Communications Cable Interconnection
CX(s) Applied: B4.7
Date: 02/10/2014
Location(s): Wyoming, Wyoming
Offices(s): Western Area Power Administration-Rocky Mountain Region

Western Area Power Administration (Western) proposes to upgrade the Cheyenne-Snowy Range (CH-SNG) Central Ring Upgrade Eaglenet Fiber Communications Cable. Western will install two fiber cables buried in two separate 2-inch conduits from Western's existing 230-kilovolt (kV) CH-SNG Transmission Line Structure 2-2 to a point of interconnect with the Eaglenet fiber line. In addition, Western will install a "hand hole" box on the west side of the Interstate 25 right-of-way boundary and directly south of the CH-SNG 230-kV Transmission Line.