You are here

CX-011994: Categorical Exclusion Determination

Marion-Alvey Marion-Lane Insulator Replacement Project
CX(s) Applied: B1.3
Date: 04/07/2014
Location(s): Oregon, Oregon
Offices(s): Bonneville Power Administration

Bonneville Power Administration is proposing to replace insulators from miles 1-20 of the Marion-Alvey and Marion-Lane transmission lines. Insulators located at the attachment points between the conductor and the transmission line towers would be accessed by helicopter.