You are here

CX-010727: Categorical Exclusion Determination

Dayton Tap Line Retirement
CX(s) Applied: B4.10
Date: 08/13/2013
Location(s): Washington
Offices(s): Bonneville Power Administration

Bonneville Power Administration (BPA) proposes to retire and remove the Dayton Tap Line (and associated components) and fund PacifiCorp’s removal of associated equipment. The Dayton Tap facility was constructed within PacificCorp’s transmission line right-of-way to establish a transmission line tap from PacificCorp’s transmission line to a BPA customer. Since the customer will no longer be served via this tap, the Dayton Tap facility is no longer needed.