You are here

CX-009719: Categorical Exclusion Determination

Repair and Line Bryan Mound Brine Tank, BMT-1
CX(s) Applied: B1.3
Date: 12/18/2012
Location(s): Texas
Offices(s): Strategic Petroleum Reserve Field Office

Subcontractor shall provide all transportation, materials, equipment, supplies, tools, facilities, utilities, labor and supervision required to repair and line the Bryan Mound (BM) brine tank, BMT-1. The tank will be cleaned by others before turning it over to the Subcontractor for repairs. Tasks include welding repair work (if required), welding inspection, tank surface preparation, and lining.