Replace Bayou Choctaw Warehouse Firewater Piping CX(s) Applied: B1.3 Date: 11/26/2012 Location(s): Louisiana Offices(s): Strategic Petroleum Reserve Field Office
Office of NEPA Policy and Compliance
November 26, 2012Replace Bayou Choctaw Warehouse Firewater Piping
CX(s) Applied: B1.3
Date: 11/26/2012
Location(s): Louisiana
Offices(s): Strategic Petroleum Reserve Field Office
Subcontractor shall provide design, plans, materials, labor and supervision required to replace the dry automatic sprinkler system found in the Bayou Choctaw Property Warehouse (Building 411). Tasks include installation and hydrostatic testing of the new sprinkler system.
CX(s) Applied: B1.3
Date: 11/26/2012
Location(s): Louisiana
Offices(s): Strategic Petroleum Reserve Field Office
Subcontractor shall provide design, plans, materials, labor and supervision required to replace the dry automatic sprinkler system found in the Bayou Choctaw Property Warehouse (Building 411). Tasks include installation and hydrostatic testing of the new sprinkler system.