Gering-Gering Valley 34.5 Kilovolt Transmission Line Underground Installation CX(s) Applied: B4.13 Date: 10/02/2012 Location(s): Nebraska Offices(s): Western Area Power Administration
Office of NEPA Policy and Compliance
October 2, 2012Gering-Gering Valley 34.5 Kilovolt Transmission Line Underground Installation
CX(s) Applied: B4.13
Date: 10/02/2012
Location(s): Nebraska
Offices(s): Western Area Power Administration
Western Area Power Administration entered into an agreement with the City of Gering to relocate 0.8 miles of Western's Gering-Gering Valley 34.5 kilovolt (kV) transmission line and Gering's two 12.47-kV distribution lines from above ground structures to underground.
CX(s) Applied: B4.13
Date: 10/02/2012
Location(s): Nebraska
Offices(s): Western Area Power Administration
Western Area Power Administration entered into an agreement with the City of Gering to relocate 0.8 miles of Western's Gering-Gering Valley 34.5 kilovolt (kV) transmission line and Gering's two 12.47-kV distribution lines from above ground structures to underground.