Replace Brine Disposal System Header to Bryan Mound Brine Tank CX(s) Applied: B1.3 Date: 08/28/2012 Location(s): Texas Offices(s): Strategic Petroleum Reserve Field Office
Office of NEPA Policy and Compliance
August 28, 2012Replace Brine Disposal System Header to Bryan Mound Brine Tank
CX(s) Applied: B1.3
Date: 08/28/2012
Location(s): Texas
Offices(s): Strategic Petroleum Reserve Field Office
Subcontractor shall provide all labor, materials, tools, equipment, and supervision required to replace the existing brine disposal piping to the Bryan Mound brine tank with new carbon steel pipe and concrete lined carbon steel pipe.
CX(s) Applied: B1.3
Date: 08/28/2012
Location(s): Texas
Offices(s): Strategic Petroleum Reserve Field Office
Subcontractor shall provide all labor, materials, tools, equipment, and supervision required to replace the existing brine disposal piping to the Bryan Mound brine tank with new carbon steel pipe and concrete lined carbon steel pipe.