Bandon-Rogue Transmission Line Rebuild Project - Fiscal Year 2012 Culvert Replacement and Associated Access Road Reconstruction CX(s) Applied: B1.3 Date: 07/06/2012 Location(s): Oregon Offices(s): Bonneville Power Administration
Office of NEPA Policy and Compliance
July 6, 2012Bandon-Rogue Transmission Line Rebuild Project - Fiscal Year 2012 Culvert Replacement and Associated Access Road Reconstruction
CX(s) Applied: B1.3
Date: 07/06/2012
Location(s): Oregon
Offices(s): Bonneville Power Administration
Bonneville Power Administration proposes to replace a failed, fish-blocking culvert with a pre-cast concrete, three sided, 15 foot span bridge and re-grade 107 feet of the streambed (including rock band structures) with natural and/or simulated streambed material.
CX(s) Applied: B1.3
Date: 07/06/2012
Location(s): Oregon
Offices(s): Bonneville Power Administration
Bonneville Power Administration proposes to replace a failed, fish-blocking culvert with a pre-cast concrete, three sided, 15 foot span bridge and re-grade 107 feet of the streambed (including rock band structures) with natural and/or simulated streambed material.