You are here

CX-008597: Categorical Exclusion Determination

Alder Stream Wind Project Feasibility Project
CX(s) Applied: A9, B3.1
Date: 07/03/2012
Location(s): Maine
Offices(s): Golden Field Office

The Department of Energy (DOE) is proposing to provide federal funding to the Penobscot Indian Nation Enterprises (Penobscot) for preconstruction and feasibility activities for the Alder Stream Wind Project on the Penobscot Indian Reservation in Franklin County (Alder Stream, Chain of Ponds, and Tim Ponds Townships) near Eustis, Maine. This proposed project would include information gathering, data analysis, modeling, mapping, cultural and wildlife surveys, and reporting.