Gila-Gila Valley Structure Replacement CX(s) Applied: B4.13 Date: 09/29/2011 Location(s): Arizona Offices(s): Western Area Power Administration-Desert Southwest Region
Office of NEPA Policy and Compliance
September 29, 2011Gila-Gila Valley Structure Replacement
CX(s) Applied: B4.13
Date: 09/29/2011
Location(s): Arizona
Offices(s): Western Area Power Administration-Desert Southwest Region
Western proposes to replace the transmission line structures and conductors of approximately 4.9 miles of the existing Gila-Gila Valley transmission line and to add an overhead ground wire.
CX(s) Applied: B4.13
Date: 09/29/2011
Location(s): Arizona
Offices(s): Western Area Power Administration-Desert Southwest Region
Western proposes to replace the transmission line structures and conductors of approximately 4.9 miles of the existing Gila-Gila Valley transmission line and to add an overhead ground wire.