Maintenance Excavation of the B-07 Outfall Ditch CX(s) Applied: B1.3 Date: 11/07/2011 Location(s): South Carolina Offices(s): Savannah River Operations Office

Office of NEPA Policy and Compliance

November 7, 2011
Estimated Read Time   min
Maintenance Excavation of the B-07 Outfall Ditch
CX(s) Applied: B1.3
Date: 11/07/2011
Location(s): South Carolina
Offices(s): Savannah River Operations Office

Maintenance excavation of the B-07 outfall ditch is needed to remove years of accumulated sediment and overgrown vegetation that is impairing flow in the ditch. The excavated area will have approximate dimensions of 5 feet wide x 40 feet long x 2 feet deep. Excavated material will be sidecast along each side of the ditch.