CX-005018: Categorical Exclusion Determination

Facility Heating, Air Conditioning, and Ventilation System Conversion to Ground Source Heat Pump (Phase 2)CX(s) Applied: A9, B5.1, B5.3Date: 01/12/2011Location(s): MontanaOffice(s): Energy Efficiency and Renewable Energy, Golden Field Office

Office of NEPA Policy and Compliance

January 12, 2011
Estimated Read Time   min
Facility Heating, Air Conditioning, and Ventilation System Conversion to Ground Source Heat Pump (Phase 2)
CX(s) Applied: A9, B5.1, B5.3
Date: 01/12/2011
Location(s): Montana
Office(s): Energy Efficiency and Renewable Energy, Golden Field Office

Flathead Electrical Cooperative (FEC) is proposing the installation and commissioning of four 20 ton geothermal open-looped heat pumps.