CX-004752: Categorical Exclusion Determination

Havre Substation Stage 03CX(s) Applied: B4.11Date: 12/13/2010Location(s): MontanaOffice(s): Western Area Power Administration-Upper Great Plains Region

Office of NEPA Policy and Compliance

December 13, 2010
Estimated Read Time   min
Havre Substation Stage 03
CX(s) Applied: B4.11
Date: 12/13/2010
Location(s): Montana
Office(s): Western Area Power Administration-Upper Great Plains Region

The Western Area Power Administration (Western) is proposing to expand the Havre Substation approximately 150 feet to the north to accommodate a new delivery service from the newly built Herron Substation by Hill County. The expansion also converts the existing 115 kilovolt single bus into a ring bus which will improve reliability. Western is also expanding the yard to the east to accommodate the replacement of the existing control building and control boards.