You are here

CX-004713: Categorical Exclusion Determination

Cloud County Community College Renewable Energy Center of Excellence
CX(s) Applied: A9
Date: 12/03/2010
Location(s): Cloud County, Kansas
Office(s): Energy Efficiency and Renewable Energy, Golden Field Office

This National Environmental Policy Act determination is for the 7 tasks listed in the April 2010 statement of project objective (uploaded in the Project Management Center) and described below for the proposed wind turbine project at Cloud County Community College. Task 1.0 - Educational Training Task 2.0 - Acquisition of Wind Turbines Task 3.0 - Erection of Wind Turbines Task 4.0 - Production of Energy Task 5.0 - Dissemination of Educational Information Task 6.0 - Business and Industry Partnerships Task 7.0 - Construction or Acquisition of Classroom/Lab Facility

DOCUMENT(S) AVAILABLE FOR DOWNLOAD