San Diego Gas and Electric Borrego Springs Microgrid Demonstration (Substation Component)
CX(s) Applied: B3.11, B4.4, B4.6, B5.1
Date: 09/22/2010
Location(s): Borrego Springs, California
Office(s): Electricity Delivery and Energy Reliability, National Energy Technology Laboratory

Install and operate utility scale diesel generator, batteries and related equipment, and components within the existing Borrego Springs substation.