Structure 57/2 Relocation on the Lovell-Thermopolis 115 Kilovolt Transmission LineCX(s) Applied: B1.3, B4.6Date: 08/23/2010Location(s): WyomingOffice(s): Western Area Power Administration-Rocky Mountain Region

Office of NEPA Policy and Compliance

August 23, 2010
Estimated Read Time   min

Structure 57/2 Relocation on the Lovell-Thermopolis 115 Kilovolt Transmission Line
CX(s) Applied: B1.3, B4.6
Date: 08/23/2010
Location(s): Wyoming
Office(s): Western Area Power Administration-Rocky Mountain Region


Western Power Administration proposes to relocate structure 57/2 on the Lovell-Thermopolis transmission line. The structure is presently located on the bank of the Greybull River, which is quickly eroding. The structure will be moved approximately 30 feet north of its present location, within the existing transmission line right-of-way. The structure is located on Wyoming State lands.