February 21, 2023

CX-028321: Cypress Yeti

N and HS personnel will be conducting 500KW generator testing over the course of the next two to three years with approximately 500 hours of operat…

September 7, 2022

CX-028318: TAN 1619 Production Support Facility Construction

The Specific Manufacturing Capability (SMC) has identified the need for design and construction of a modern facility (TAN-1619) to support existing…

February 5, 2021

CX-023251: K-Area CCO Storage Pad Fighting Position

Security requires the addition of a fighting station inside the outer Restricted Area concrete block barrier, north of the KCCO Storage Pad (163-70…

December 15, 2020

CX-023006: Electrical Enhancements at 741-2N for CCO Storage Pad Systems Testing

Electrical enhancements at 741-2N for CCO Storage Pad systems testing, primarily to supply/upgrades for electrical demand/need.…

September 16, 2020

CX-022464: Construction of Concrete Storage Pad with Soft Enclosure, K-Area

The proposed activity will involve removing the currently approved palletized operations on the CCO pad to utilize a rack system for horizontal con…

August 5, 2020

CX-270534: Hazardous Waste Permit Modification to Create a Treatment and Storage Facility

NNSA proposes to use LANL, TA-60, Bldg 17, as a treatment and storage facility.

July 15, 2020

CX-022044: Two New Storage Pads at ATR Complex

Construct two new storage pads at the north end of the ATR Complex forheavy equipment and other non-radiological material storage and for low-level…

August 21, 2019

CX-020795: Pad Installations at TRA-1710 and TRA- 605

In 2012, Idaho National Laboratory (INL) proposed to move the low-level radioactive waste (LLW) stored on the pad at building Test Rector Area (TRA…

January 15, 2019