Kersey West Switching Station Interconnection Kiowa Creek - Welc 115 Kilovolt Transmission Line
CX(s) Applied: B4.1, B4.11
Date: 01/23/2013
Location(s): Colorado
Offices(s): Western Area Power Administration-Rocky Mountain Region
Existing Regulations
B4.11: Electric power substations and interconnection facilities
Construction or modification of electric power substations or interconnection facilities (including, but not limited to, switching stations and support facilities).
Previous Regulations
Categorical Exclusion Determinations dated before November 14th, 2011 were issued under previous DOE NEPA regulations. See the Notice of Final Rulemaking (76 FR 63763, 10/13/2011) for information changes to this categorical exclusion.
DOCUMENTS AVAILABLE FOR DOWNLOAD
-
January 23, 2013
-
December 4, 2012
Keeler Substation-Control House Expansion
CX(s) Applied: B4.11
Date: 12/04/2012
Location(s): Oregon
Offices(s): Bonneville Power Administration -
November 8, 2012
Snohomish Substation Control House Expansion & Seismic Retrofit
CX(s) Applied: B4.11
Date: 11/08/2012
Location(s): Washington
Offices(s): Bonneville Power Administration -
September 28, 2012
Bucknum Substation Construction
CX(s) Applied: B4.11
Date: 09/28/2012
Location(s): Wyoming
Offices(s): Western Area Power Administration-Rocky Mountain Region -
August 23, 2012
Midstate Electric Cooperative, Inc, Integration Request, Line and Load Interconnection Request L0296
CX(s) Applied: B4.11
Date: 08/23/2012
Location(s): Oregon
Offices(s): Bonneville Power Administration -
August 14, 2012
Raver Substation-Control House Expansion & Seismic Retrofit
CX(s) Applied: B4.11
Date: 08/14/2012
Location(s): Washington
Offices(s): Bonneville Power Administration -
August 9, 2012
Optimization of Electrical Power at the Portsmouth Gaseous Diffusion Facility
CX(s) Applied: B4.6, B4.11
Date: 08/09/2012
Location(s): Ohio
Offices(s): Portsmouth Paducah Project Office -
August 8, 2012
Sno-King Substation Expansion
CX(s) Applied: B4.11
Date: 08/08/2012
Location(s): Washington
Offices(s): Bonneville Power Administration -
July 30, 2012
Line Switch Replacements at Guernsey Rural, Worland, Refinery, Box Butte, and Morrill Taps
CX(s) Applied: B4.6, B4.11
Date: 07/30/2012
Location(s): Wyoming, Nebraska
Offices(s): Western Area Power Administration-Rocky Mountain Region -
July 25, 2012
Line Switch Replacements at Chappell and Julesburg Taps in Deuel County, Nebraska and Kersey Tap in Weld, Colorado
CX(s) Applied: B4.6, B4.11
Date: 07/25/2012
Location(s): Nebraska, Colorado
Offices(s): Western Area Power Administration-Rocky Mountain Region -
July 25, 2012
Midway Substation 230 Kilovolt Upgrades El Paso County, Colorado
CX(s) Applied: B4.6, B4.11
Date: 07/25/2012
Location(s): Colorado
Offices(s): Western Area Power Administration-Rocky Mountain Region -
June 13, 2012
Utility Corridor Extension
CX(s) Applied: B4.7, B4.11, B5.2, B5.5
Date: 06/13/2012
Location(s): Pennsylvania
Offices(s): Naval Nuclear Propulsion Program, Bettis Site -
March 29, 2012
Terry Ranch Road Substation
CX(s) Applied: B1.24, B4.11
Date: 03/29/2012
Location(s): Wyoming
Offices(s): Western Area Power Administration-Rocky Mountain Region -
March 7, 2012
Archer Communications Building Laramie County, Wyoming
CX(s) Applied: B4.6, B4.11
Date: 03/07/2012
Location(s): Wyoming
Offices(s): Western Area Power Administration-Rocky Mountain Region -
February 14, 2012
Grant County Public Utility District - Columbia Substation Interconnection Project
CX(s) Applied: B4.11
Date: 02/14/2012
Location(s): Washington
Offices(s): Bonneville Power Administration -
January 18, 2012
General Motors Battery Pack Assembly Plant - Electric Substation Upgrade
CX(s) Applied: B4.11
Date: 01/18/2012
Location(s): Michigan
Offices(s): National Energy Technology Laboratory -
October 11, 2011
Bristol to Groton Transmission Line Upgrade Project
CX(s) Applied: B4.11
Date: 10/11/2011
Location(s): South Dakota
Office(s): Western Area Power Administration-Upper Great Plains Region -
September 27, 2011
Cattle Creek Substation
CX(s) Applied: B4.11
Date: 09/27/2011
Location(s): Bonneville County, Idaho
Office(s): Bonneville Power Administration -
September 15, 2011
Maxwell - O'Banion Optical Ground Wire
CX(s) Applied: B1.7, B4.6, B4.7, B4.11
Date: 09/15/2011
Location(s): Sutter County, California
Office(s): Western Area Power Administration-Sierra Nevada Region, National Energy Technology Laboratory -
July 14, 2011
Movement of the Shirley Pump Substation To a New Site and Replacement of the Shirley Pump Substation Transformer
CX(s) Applied: B4.11
Date: 07/14/2011
Location(s): Montana
Office(s): Western Area Power Administration-Upper Great Plains Region -
July 14, 2011
Interconnection of the Pronghorn Gas Plant 115 Kilovolt Transmission Line
CX(s) Applied: B4.11
Date: 07/14/2011
Location(s): Montana
Office(s): Western Area Power Administration-Upper Great Plains Region -
July 14, 2011
Addition of a New Substation Near Lake Bowdoin, Montana
CX(s) Applied: B4.11
Date: 07/14/2011
Location(s): Lake Bowdoin, Montana
Office(s): Western Area Power Administration-Upper Great Plains Region -
July 14, 2011
Circle Substation Expansion
CX(s) Applied: B4.11
Date: 07/14/2011
Location(s): Montana
Office(s): Western Area Power Administration-Upper Great Plains Region -
July 8, 2011
Interconnection of the Letcher to Mitchell 115 Kilovolt Transmission Line to Western's Letcher Substation
CX(s) Applied: B4.11
Date: 07/08/2011
Location(s): Montana
Office(s): Western Area Power Administration-Upper Great Plains Region -
June 8, 2011
North Oakes Tap of the Edgeley to Forman 69 Kilovolt line
CX(s) Applied: B4.11
Date: 06/08/2011
Location(s): North Dakota
Office(s): Western Area Power Administration-Upper Great Plains Region