Line and Load Interconnection of Coos-Curry Electric Cooperative?s New Substation to Bonneville Power Administration?s Fairview-Bandon 115-Kilovolt Transmission Line
CX(s) Applied: B4.6, B4.10
Date: 09/26/2011
Location(s): Coos County, Oregon
Office(s): Bonneville Power Administration
Existing Regulations
B4.10: Removal of electric transmission facilities
Deactivation, dismantling, and removal of electric transmission facilities (including, but not limited to, electric powerlines, substations, and switching stations) and abandonment and restoration of rights-of-way (including, but not limited to, associated access roads).
Previous Regulations
Categorical Exclusion Determinations dated before November 14th, 2011 were issued under previous DOE NEPA regulations. See the Notice of Final Rulemaking (76 FR 63763, 10/13/2011) for information changes to this categorical exclusion.
DOCUMENTS AVAILABLE FOR DOWNLOAD
-
September 26, 2011
-
December 23, 2010
New Power Line for New Generator at Ten Sleep
CX(s) Applied: B1.3, B4.6, B4.10, B4.12, B5.1
Date: 12/23/2010
Location(s): Casper, Wyoming
Office(s): RMOTC -
February 24, 2010
183-2C Removal of Switchgear Cubicle
CX(s) Applied: B4.10
Date: 02/24/2010
Location(s): Aiken, South Carolina
Office(s): Environmental Management, Savannah River Operations Office -
February 2, 2010
Electrical Isolation and Pole Removal, 13.8 kilovolt Section in F-Area
CX(s) Applied: B4.10
Date: 02/02/2010
Location(s): Aiken, South Carolina
Office(s): Environmental Management, Savannah River Operations Office -
September 21, 2009
Electrical Isolations at 740-A Trailer Complex
CX(s) Applied: B4.10
Date: 09/21/2009
Location(s): Aiken, South Carolina
Office(s): Environmental Management, Savannah River Operations Office -
September 9, 2009
Electrical Isolation of 652-68G and 652-70G Transformers
CX(s) Applied: B4.10
Date: 09/09/2009
Location(s): Aiken, South Carolina
Office(s): Environmental Management, Savannah River Operations Office -
August 5, 2009
Electrical Isolation of Building 710-B
CX(s) Applied: B4.10
Date: 08/05/2009
Location(s): Aiken, South Carolina
Office(s): Environmental Management, Savannah River Operations Office