Independent Oversight Review, Y-12 National Security Complex - June 2012

June 2012

Review of the Y-12 Implementation Verification Review Processes

This report documents the independent review of implementation verification review (IVR) processes at the Y-12 National Security Complex (Y-12) conducted by the Office of Enforcement and Oversight (Independent Oversight, Office of Safety and Emergency Management Evaluations), within the Office of Health, Safety and Security (HSS). The review was performed from March 12 - 30, 2012. The objective of this review was to evaluate the extent to which the site management and operating contractor, B&W Y-12, a partnership of Babcock & Wilcox and Bechtel Corporation, and the Y-12 Site Office (YSO) have developed and employed appropriate implementation verification methods.