August 8, 2018
Enterprise Assessments Assessment of the Hanford Site Waste Treatment and Immobilization Plant Low-Activity Waste Facility Documented Safety Analysis, Technical Safety Requirements, and Safety Evaluation Report - August 2018
Assessment of Documented Safety Analysis, Technical Safety Requirements, and Safety Evaluation Report at the Hanford Site Waste Treatment
March 5, 2018
Enterprise Assessments Assessment of the Hanford Site Waste Treatment and Immobilization Plant Construction Quality – March 2018
Assessment of Construction Quality at the Hanford Site Waste Treatment and Immobilization Plant
February 28, 2018
Enterprise Assessments Follow-up Assessment of Progress on Actions Taken to Address Tank Vapor Concerns at the Hanford Site – February 2018
Follow-up Assessment of Progress on Actions Taken to Address Tank Vapor Concerns at the Hanford Site
February 9, 2018
Enterprise Assessments Assessment of Low-Level Radioactive Waste Disposal Practices at the Hanford Site – February 2018
Assessment of Low-Level Radioactive Waste Disposal Practices at the Hanford Site
December 21, 2017
Enterprise Assessments Targeted Assessment of the Hanford Site Tank Farms Low Activity Waste Pretreatment System Preliminary Safety Design Basis – December 2017
Targeted Assessment of the Low Activity Waste Pretreatment System Preliminary Safety Design Basis at the Hanford Site Tank Farms
November 16, 2017
Assessment of the Hanford Site Waste Treatment and Immobilization Plant Construction Quality – November 2017
Conducted an independent assessment of construction quality at the Hanford Site Waste Treatment and Immobilization Plant (WTP).
August 25, 2017
Assessment of the Hanford Site Waste Treatment and Immobilization Plant Construction Quality – August 2017
Construction Quality Assessment at the Hanford Site Waste Treatment and Immobilization Plant
April 24, 2017
Enterprise Assessments Assessment of the Hanford Site Waste Treatment and Immobilization Plant Construction Quality – April 2017
Assessment of the Hanford Site Waste Treatment and Immobilization Plant Construction Quality – April 2017
January 11, 2017
Enterprise Assessments Follow-up Assessment of Progress on Actions Taken to Address Tank Vapor Concerns at the Hanford Site – January 2017
Follow-up Assessment of Progress on Actions Taken to Address Tank Vapor Concerns
December 30, 2016
Enterprise Assessments Assessment of the Hanford Site Waste Treatment and Immobilization Plant Construction Quality – December 2016
Assessment of Construction Quality, Hanford Site Waste Treatment and Immobilization Plant